Altenberge: Industrial estate development project

Here you will find all the key information on broadband roll-out in the industrial estates of the municipality of Altenberge.

The expansion is funded by the Federal Ministry of Digital and Transport and the Ministry of
Economic Affairs, Industry, Climate Protection and Energy of the State of North Rhine-Westphalia.

The development area

Number of addresses covered: 120

Contractor: epcan & Muenet joint venture

Civil engineering: 6.623 km

Empty conduits: 43.54 km

Fibre optic cables: 21.54 km

Operating deficit: €988,067.00

Federal government: EUR 494,033.50

State: €395,226.80

Local authority: €98,806.70

Construction progress *

0
Construction progress (%)

* The civil engineering works are in their final stages. House connections are currently being installed and activated.

Milestones

  • Application submitted: June 2020
  • Provisional funding decision: August 2020
  • State co-funding commitment: November 2020
  • Call for proposals: March 2021 to June 2021

     

  • Contract awarded: October 2021
  • Construction phase: August 2022 to March 2024
  • Final application: October 2022
  • Project completion: February 2024

As of January 2026