The development area

Number of addresses covered: 126

Provider: osnatel (EWE TEL GmbH)

Civil engineering: 7.512 km

Empty conduits: 10.361 km

Fibre optic cables: 2.17 km

Funding shortfall: €493,228.00

Federal government: €246,614.00

State: €197,291.20

Local authority: €49,322.80

Construction progress *

0
Construction progress (%)

* The civil engineering works are in their final stages. House connections are currently being installed and activated.

Milestones

  • Application submitted: June 2020
  • Provisional funding decision: August 2020
  • State co-funding commitment: November 2020
  • Call for proposals: March 2021 to June 2021
  • Award: August 2021
  • Final application: March 2022
  • Implementation phase: June 2022 to September 2023
  • Final decision: August 2022
  • Project completion: September 2023