Lotte: Industrial Estate Development Project

Here you will find all the key information on broadband roll-out in the industrial estates of the municipality of Lotte.

The expansion is funded by the Federal Ministry of Digital and Transport and the Ministry of
Economic Affairs, Industry, Climate Protection and Energy of the State of North Rhine-Westphalia.

The development area

Number of addresses supported: 165

Provider: Telekom

Civil engineering: 4.16 km

Empty conduits: 51.928 km

Fibre optic cables: 5.571 km

Funding shortfall: €533,609.00

Federal government: EUR 266,804.50

State: €213,443.60

Local authority: €53,360.90

Construction progress *

0
Construction progress (%)

* The civil engineering works are in their final stages. House connections are currently being installed and activated.

Milestones

  • Application submitted: June 2020
  • Provisional funding decision: August 2020
  • State co-funding commitment: November 2020
  • Call for proposals: March 2021 to June 2021
  • Award: October 2021
  • Final application submission: May 2022

  • Final decision: December 2022

  • Implementation phase: November 2024 to September 2025

  • Project completion: September 2025

As of January 2026