Mettingen: Industrial estate development project

Here you will find all the key information on broadband roll-out in the industrial estates of the municipality of Mettingen.

The expansion is funded by the Federal Ministry of Digital and Transport and the Ministry of
Economic Affairs, Industry, Climate Protection and Energy of the State of North Rhine-Westphalia.

The development area

Number of addresses covered: 50

Provider: osnatel (EWE TEL GmbH)

Civil engineering: 3.023 km

Empty conduits: 7.03 km

Fibre optic cables: 2.129 km

Operating deficit: €293,499.00

Federal government: EUR 146,749.50

State: €117,399.60

Local authority: €29,349.90

Construction progress *

0
Construction progress (%)

* The civil engineering works are in their final stages. House connections are currently being installed and activated.

Milestones

  • Application submitted: June 2020
  • Provisional funding decision: August 2020
  • State co-funding commitment: November 2020
  • Call for proposals: March 2021 to June 2021
  • Award: August 2021
  • Final application submission: March 2022
  • Implementation phase: May 2022 to September 2023
  • Final decision: October 2022
  • Project completion: September 2023

As of January 2026