Number of addresses covered: 162

Provider: Telekom

Civil engineering: 5,405 km

Empty conduits: 12,667 km

Fibre optic cables: 23,653 km

Funding shortfall: €521,162.00

Federal government: EUR 260,581.00

State: €208,464.80

Local authority: €52,116.20

Construction progress *

0
Construction progress (%)

* The civil engineering works are in their final stages. House connections are currently being installed and activated.

Milestones

  • Application submitted: June 2020
  • Provisional funding decision: August 2020
  • State co-funding commitment: November 2020
  • Call for proposals: March 2021 to September 2021
  • Award: November 2021

  • Final application: May 2022

  • Implementation phase: January 2024 to December 2024

  • Project completion: December 2024

     

     

     

     

     

     

     

     

     

     