Steinfurt: Industrial estate development project

Here you will find all the key information on broadband expansion in the industrial estates of the town of Steinfurt.

The expansion is funded by the Federal Ministry of Digital and Transport and the Ministry of
Economic Affairs, Industry, Climate Protection and Energy of the State of North Rhine-Westphalia.

The development area

Number of addresses covered: 105

Supplier: Stadtwerke Steinfurt GmbH

Civil engineering: 6.515 km

Empty conduits: 42.613 km

Fibre optic cables: 53.171 km

Funding shortfall: €693,518.00

Federal Government: EUR 346,759.00

State: €277,407.20

Local authority: €69,351.80

Construction progress *

0
Construction progress (%)

* The civil engineering works are in their final stages. House connections are currently being installed and activated.

Milestones

  • Application submitted: June 2020
  • Provisional funding decision: August 2020
  • State co-funding commitment: November 2020
  • Call for proposals: March 2021 to June 2021
  • Award: August 2021
  • Final application submission: July 2023

  • Final decision: December 2023

  • Implementation phase: October 2024 to December 2025

  • Project completion: December 2025

As of January 2026